Prev: Exterior nailing inspection fail and pass
(12 total pages) Click on any for a larger view Next: Awaiting a permit
| ||||
| ||||
Wrapping the building Inspection passed at last, the building gets wrapped. To be continued.
| ||||
Bruce begins to apply paper | Wrapping is far along | |||
Wrapping the building. Thanks to a friend I acquired 24 more sections of scaffolding. These I gradually deploy with each visit to the site, removing the improvisations I had erected earlier. |
At last some exterior walls may be wrapped; February 18. But "this horse left the barn" long ago. The rainy season is waning.
| ||
Feb 26 - The SE passed the nailing. The whole exterior can be wrapped. On Feb 26 it is about 75%.
| ||