Prev: Awaiting a permit   (12 total pages) Click on any for a larger view   Next: Level 1 Joists
Pages
Excavation     July 29, 2023, nearly four years and $ tens of thousands after permit application.
At this date Noriko is zero percent on board this project.
Indicating the perimeter Expensive guys push dirt around Footing poured, without inspection
Forms Correction per geotech study Foundation poured at last
Forms stripped Cleaning up after concrete After back-fill around the foundation
Submission of the permit application in Dec 2019 commenced 2 1/2 years of woe.
Signing the concrete contract on 7/17/2022 commenced another year of woe.


1. Indicating the perimeter
Transforring the plan to the ground was no snap. Bruce had hoped the veteran contractor could do this himself using my EMT perimeter as an aid. That is not what happened.
_22aug13-mcn_0021.jpg
Alvin, our concrete contractor. Am I willing to hire him again?
_22aug13-mcn_0020a.jpg
Help! the contractor called. Bruce had to visit a couple times to help mark the foundation perimeter.
_22aug13-mcn_0017a.jpg
Alvin and I struggle to pint down the perimeter.
_22aug13-mcn_0019.jpg
_22aug04-mcb_1120.jpg
Some excavation has occured.
_22aug04-mcb_1120b.jpg
_22aug04-mcb_1120c.jpg
_22aug04-mcb_1121.jpg
_22aug13-mcn_0017.jpg
_22aug13-mcn_0229.jpg
The road association annunal meeting had to put up with the excavating machiines.
_22aug20-mcn_0021.jpg
_22aug20-mcn_0022.jpg
_22aug27-mcn_0307.jpg
_22aug27-mcn_0308.jpg


2. Expensive guys push dirt around
The $150/hr excavator guys push dirt hither, then thither; enjoying the weather and taking snapshots of bears - when I was not there to question.
_22aug20-mc_0755.jpg
_22aug20-mc_0756.jpg


3. Footing poured, without inspection
There is a lot of labor and craft to this work.
But Alvin poured the grade beam without a prior county inspection. He had "reasons," he said. That is when our woe began.
_25feb14-mcb_1259.jpg
_25feb14-mcb_1259a.jpg
This is the corner which subsequently caused trouble.
_25feb14-mcb_1300a.jpg
_25feb14-mcb_1300c.jpg
_22sep04-mcn_0716.jpg
_22sep04-mcn_0716a.jpg
_22oct03-mcn_0058.jpg


4. Forms
Forms competently in place, October 2022. Alvin expected to call for concrete the day following inspection. The inspected halted the project.
_22oct08-mcn_2305.jpg
October 2022.
_22oct08-mcn_2307.jpg
_23jan15-mcb_1434.jpg
January 15 - no change
_23jan21-mcn_0054.jpg
January 2023. The job is still at a halt.
_23jan21-mcn_0055.jpg
_23may13-mcn_0024.jpg
May 2023. Note the vigorous spring grass. No progress.


5. Correction per geotech study
At last a geotech study was executed. Based on it the structural engineer added support piers at the corner nearest the slope. These had to be hand-dug. It is June 2023. This delay cost most of a year.
_23jun10-mcb_1942.jpg
_23jun10-mcb_1942a.jpg
_23jun10-mcb_1942b.jpg
_23jul02-mcn_2343.jpg
_23jul07-mcn_2258.jpg
_25feb14-mcb_1300d.jpg
_25feb14-mcb_1300e.jpg


6. Foundation poured at last
July 2023. The inspector O.K.s the project. Concrete is at last poured.
_23jul21-mcn_2358.jpg


7. Forms stripped
Forms ae stripped. The contractor has pulled out. I am surprised at the quality. Alvin actually pulled it off. I write the last of several huge checks.
Noriko shows her disdain for this whole project.
_23jul28-mcn_2154.jpg
_23jul28-mcn_2155.jpg
_23jul28-mcn_2157.jpg
At this corner appear the added subterranean piers resulting from the geotech finding.
_23jul28-mcn_2159a.jpg
_23jul29-mcb_1957.jpg
_23jul29-mcb_1957b.jpg


8. Cleaning up after concrete
The contractor left some clean-up issues.
_23aug05-mcb_1832.jpg
_23aug05-mcb_1833.jpg
A lot of hand-excavated dirt had been heaved over the hill.
_23aug05-mcb_1835.jpg
Concrete pumping hose sprang leaks a couple times, spraying concrete over the landscape.
_23aug05-mcb_1836.jpg


9. After back-fill around the foundation
I hired Antonio Soto, local contractor, to back-fill the foundation. The concrete contractor should have done this but probably would have charged a ridiculous amount extra.
_23dec03-mcb_1159.jpg
_23dec03-mcb_1200a.jpg
_24jan02-mcb_1148.jpg
Winter 2023-24 turned the exposed dirt into a muddy mess.
Prev: Awaiting a permit   (12 total pages) Click on any for a larger view   Next: Level 1 Joists

Automatically generated by "UrAlbum" script-driven software by Bruce Wicinas © 2005-2025. Not phone-friendly (use a real screen.) 250318