Prev: Awaiting a permit
(12 total pages) Click on any for a larger view Next: Level 1 Joists
| ||||
| ||||
Excavation July 29, 2023, nearly four years and $ tens of thousands after permit application. At this date Noriko is zero percent on board this project. | ||||
Indicating the perimeter | Expensive guys push dirt around | Footing poured, without inspection | ||
Forms | Correction per geotech study | Foundation poured at last | ||
Forms stripped | Cleaning up after concrete | After back-fill around the foundation | ||
Submission of the permit application in Dec 2019 commenced 2 1/2 years of woe. Signing the concrete contract on 7/17/2022 commenced another year of woe. |
Transforring the plan to the ground was no snap. Bruce had hoped the veteran contractor could do this himself using my EMT perimeter as an aid. That is not what happened.
| ||
The $150/hr excavator guys push dirt hither, then thither; enjoying the weather and taking snapshots of bears - when I was not there to question.
| ||
There is a lot of labor and craft to this work.
But Alvin poured the grade beam without a prior county inspection. He had "reasons," he said. That is when our woe began. | ||
Forms competently in place, October 2022. Alvin expected to call for concrete the day following inspection. The inspected halted the project.
| ||
At last a geotech study was executed. Based on it the structural engineer added support piers at the corner nearest the slope. These had to be hand-dug. It is June 2023. This delay cost most of a year.
| ||
July 2023. The inspector O.K.s the project. Concrete is at last poured.
| ||
Forms ae stripped. The contractor has pulled out. I am surprised at the quality. Alvin actually pulled it off. I write the last of several huge checks.
Noriko shows her disdain for this whole project. | ||
The contractor left some clean-up issues.
| ||
I hired Antonio Soto, local contractor, to back-fill the foundation. The concrete contractor should have done this but probably would have charged a ridiculous amount extra.
| ||