L2 Floor     The great beams and floor trusses of L2 floor seemgingly fly into place.
L2 beams and trusses Panic due to unseasonal August rain  
Level 2 Floor Framing. The framers had more then proved themselves, so we advance. This presented much greater challenge, to my eye, than the wall framing below.


1. L2 beams and trusses
Framers had to rent a lift to raise these beams 10 feet.
_l2floorframing.jpg
_24aug10-mcn_1835.jpg
These beams suddenly appear.
_24aug10-mcn_1836.jpg
_24aug10-mcn_1837.jpg
_24aug15-mcb_1215a.jpg
_24aug15-mcb_1238b.jpg
_24aug15-mcb_1238.jpg
_24aug15-mcb_1238a.jpg
_24aug20-mcn_1231.jpg
The structural engineer (SE) visits for a consulation. The framers had raised some questions.
_24aug31-mcn_1234.jpg
The great atrium opening is now evident. No one but the structural engineer knew about this. Noriko had never seen the building drawings.
_24sep01-mcb_0935.jpg
Framers partially frame over the atrium opening to faciliate subsequent framing.
_24sep21-mcn_1144a.jpg
14" LSL detail.
_24oct02-mcb_1302.jpg
_24aug20-mcna_1258.jpg


2. Panic due to unseasonal August rain
August 25 - significant rain is predicted. This is off the charts. The level 2 floor plywood is completely vulnerable. I spend a day deploying a 40x30' tarp, 10 sheets of plywood and 25 sheets of roofing metal.
_24aug25-mcb_1108.jpg
_24aug25-mcb_1108a.jpg
_24aug25-mcb_1108b.jpg
_24aug25-mcb_1109.jpg
_24aug20-mcna_1738.jpg